Mick has finished changing the bench seats in Block A, however, he has now used up all the spare brackets. We will need to order more brackets before starting block G. He has also been breaking up the damaged concrete areas and re-instating around the Main Stand/Cut Throat Lane turnstiles.
Alan has returned this week after being off for a couple days. He has started painting the doors on the NRE / Corona turnstiles. The eight doors will take about two weeks to complete
Wendy has given a few more locations a spring clean including the control room and the sports fitness centre front lobby.
Les has continued to paint the great wall of the Habbin. It is looking much brighter now. He has almost got all away along. It has been a massive job and taken a lot of willpower not to leave and do something else. I keep asking if he wants to start final floodlight to give him a break.
Giac has continued doing the concreting in the NRE/Corona End. This is now complete. He has moved on to the next job, modifing and felting the new shed.
The group has re-painted the roadway and floor signage around the ground.
Brian has been helping me with a project which required moving a large quantity of items from one location to another.
Glen has been doing some electrical work around the ground. He also does all the PAT tests
We have now been asked to complete some work at the Training Centre. This has been surveyed and is planned in for the 10th June.